JAVA 1 – 500kV Over Head Transmission Line Project

Project Name: JAVA 1 – 500kV Over Head Transmission Line Project

Owner: PLN/Marubeni/IPP

Main Contractor: Samsung C&T

Subcontractor : PT Berca Buana Sakti-ETI

Total Tower : 118 Towers

Project Duration: 660 Days

The Location is from Cilamaya, Karawang, West Java to Cibatu Baru, West Java

Scope of Works:

  1. Soil Investigation to determine Foundation Type for the tower to stand still
  2. Site Survey to determine the coordinate of each tower and the wind span.
  3. Engineering Works: Foundation and Tower Design
  4. Procurement Works: Tower, Insulator, Conductor and fitting and accessories
  5. Construction Work:
    1. Foundation work
    2. Tower Erection
    3. Stringing
  6. Commisioning